HomeFeedbackSite mapRussian version

Investment program

  1. Investment program
  2. Reconstruction of Sheskharis Oil Terminal (Stages 1 and 2)
  3. Construction of Fuel Oil Terminal (NCSP Group's stake in the project is 50%), Pier 4 reconstruction
  4. Construction of bunkering complex in Primorsk
  5. Container terminal construction at Baltiysk
  6. IPP reconstruction, storage facilities replacement; bunkering terminal expansion at IPP
  7. IPP reconstruction, storage facilities replacement
  8. Grain
  9. Iron ore
  10. Other cargo
  11. Primorsk

Implementation of projects under existing investment program

As part of the continued implementation of the investment program that was adopted by NCSP Group's previous management, $416 million of the planned $538 million had been spent by the end of 2011. The program focused on construction of new terminals (Sheskharis Oil Terminal, Novorossiysk Fuel Oil Terminal, BSC). This program will expand capacity across the Group by 5.5 million-20.5 million tonnes and 238,000 TEU.

Reconstruction of Sheskharis Oil Terminal (Stages 1 and 2)

Back to top

Project Highlights

Construction period - 2006-2013
Planned capacity - +15 mln tonnes p/a
Investments - $145.7 mln
Invested to date - $113.8 mln
Planned investments in 2012 - $23.2 mln
Planned investments in 2013 - $8.7 mln

Objective

Construction of the terminal Рђ with capacity of 50 mln tons to ensure capital repairs at the terminal B
Possibility to admit vessels with 150 thousand tons DWT, which are currently served at the berth B
Automatization of oil control and metering system

Planned results

Terminal capacity to increase up to 65 mln tons of oil per annum (65 mln tons = main pipeline limitation)
Possibility to reconstruct terminal B with no adverse effect on through put volumes

Construction of Fuel Oil Terminal (NCSP Group's stake in the project is 50%), Pier 4 reconstruction

Back to top

Project Highlights

Construction period - April 2010-Q1 2012
Capacity - 4 mln tonnes p/a
Investments - $223.6 mln
Invested to date - $200.1 mln
Planned investments in 2012 - $23.5mln

Objective

Construction of a modern fuel oil terminal with capacity of 4 mln tons per annum through a 50-50 joint venture with a major international oil trader
Dredging up to 13.5 m and reconstruction of Pier No.4, to enable to admit vessels with 45 thousand tones DWT(the pier was previously not in operation)

Planned results

Redirection of Russian oil products going through the ports of Ukraine
278 additional jobs created

Construction of bunkering complex in Primorsk

Back to top

Project Highlights

Construction period - March 2010 - Q1 2012
Capacity - 410 thousand tonnes p/a
Investments - $61.0 mln
Invested to date - $55.8 mln

Objective

Construction of bunkering complex with the capacity of 410 thousand tons per annum has been completed
Before the launch of the complex, bunkering services were offered by other operators' vessels, which resulted in additional costs and environmental risks

Planned results

To decrease mooring time at berth - cost reduction for cargo owners
To reduce risk of interaction of two ships with hazardous cargoes (bunkering vessel and tanker)
To reduce costs for hiring pilots and for implementation of oil spill prevention measures
To increase transshipment volumes due to beginning of a) supply of bunkering fuel for export and b) delivery of bunkering fuel by railway
The project will allow PTP to obtain higher return on existing assets and to become more technologically advanced and attractive port for counterparts

Current Situation

Construction of bunkering facility completed
Potential to start loading fuel for export

Container terminal construction at Baltiysk

Back to top

Project Highlights

Construction period - Jan. 2010 - Q4 2013
Planned capacity - 400 thousand TEU
Investments - $87.5 mln
Invested to date - $40.8 mln
Planned investments in 2012 - $1.9 mln
Planned investments in 2013 - $44.8 mln

Objective

Construction of a modern container terminal with capacity of 400 thousand TEU for Kaliningrad region needs

Key changes

Container throughput increase is possible due to existing clients' volumes growth, as well as due to attraction of new shipping lines
Terminal capacity of 200 thousand TEU has been reached, planned capacity increase of up to 400 thousand TEU as the new cargo base is secured
General cargo handling is being Considered

Current Situation

Completion of construction of the first phase of container terminal with capacity of 200 thousand TEU for Kaliningrad region needs
Continuation of the project with the target capacity increase up to 400 thousand TEU

IPP reconstruction, storage facilities replacement; bunkering terminal expansion at IPP

Back to top

Bunkering terminal expansion at IPP

Project Highlights

Construction period - Feb. 2012.- Sept. 2012
Planned capacity - +96 thousand tonnes p/a
Investments - $2.2 mln
Invested to date - $0.2 mln

Objective

Expansion of the existing storage park via construction of a new tank with capacity of 5 thousand cubic meters

Planned results

Increase of bunkering volumes by 96 thousand tons per annum Multi-purpose of the the bunkering complex, export perspectives Creation of additional competitive advantages for IPP on the bunkering market of Novorossiysk

Current Situation

Project documentation is ready Glavgosexpertiza approval is obtained Construction and installation works are being implemented

IPP reconstruction, storage facilities replacement

Back to top

Project Highlights

Construction period - Sept. 2010 - Nov. 2012
Planned capacity - +1 mln tonnes
Investments - $18.3 mln
Invested to date - $5.0 mln

Objective

Increase of existing capacities of IPP by replacing old tanks with new highervolume diesel fuel tanks and reconstruction of other technological equipment

Planned results

Replacement of 4 worn-out tanks with capacity of 20 000 cubic meters with 3 new tanks with capacity of 30 000 cubic meters to handle up to 6 mln tons of diesel fuel per annum and up to 1 mln tons of oil products Scheduled reconstruction period of 16 months, of which

  • 7 months to execute project and engineering works
  • 9 months to execute construction and installation works

New development concept

Within the context of the Master Plan, management is proposing a new concept for NCSP Group's growth in the period to 2020 that calls for transition from specialization by stevedoring company to specialization by production area, with a focus on high-margin cargo. The cost of the new investment program is estimated at $1.0 - $1.1 billion.

The priorities of the new concept for NCSP Group's growth are:

  • Development of container business
  • Specialization of NLE in handling containers. Construction of a specialized container terminal with throughput capacity of 500,000 TEU
  • Construction of container terminal in NCSP's Western Area, which will expand container throughput capacity at NCSP to 700,000 TEU from 170,000 TEU
  • Expansion of the range of services offered by acquiring and developing land at the port
  • Expansion of grain throughput capacity at Novorossiysk Port by 2 million tonnes
  • Construction of terminal to handle iron ore products with throughput capacity of up to 12 million tonnes, with possible use of technology to allow handling of other types of bulk cargo (mineral fertilizer, coal) and reverse cycle operation
  • Modernization of cargo handling equipment at NCSP's Eastern Area and NSRZ; relocation of pipes, ferrous and nonferrous metals, timber products (possibly), perishable goods, outsized and other types of cargo to the Eastern Area of NCSP and NSRZ
  • Transformation of Primorsk Trade Port into a universal deepwater port, setting the stage for increasing Russia's export potential, and diversification of the business with a long-term program for construction of terminals at Primorsk to handle oil products and, possibly, containers, general and bulk cargo

Containers

The Company's priority is to expand its container business. There were three options for expanding container turnover in Novorossiysk.

Management chose the least costly and least risky option for achieving the desired result, which calls for gradually expanding the existing container terminals at NLE and NCSP to respectively 500,000 TEU and 700,000 TEU, and the construction of an inland container terminal in Novorossiysk. The construction of the inland container terminal will significantly expand the range of services offered at NLE, boost revenue per TEU and lay the foundation for building the NCSP logistics chain. For the construction of the inland container terminal, the Company plans to buy a plot of land at the Novorossiysk port, on which it could spend $30 million-$ 40 million.

Construction of specialized container terminal at NLE

The first phase of the Group's strategy to increase container turnover will be the construction of a specialized container terminal at NLE with throughput capacity of up to 500,000 TEU with an average storage period of 10 days. This project is to be carried out in 2012-2014. In the course of terminal construction, there are plans to conduct dredging works at NLE berths No. 28 and No. 28A, which will enable them to accommodate direct ocean lines with capacity of 5,000 TEU, and thus attract new customers.

Construction of NCSP container terminal

Once throughput capacity at NLE is at least 75% utilized, the Group will begin the project to build a container terminal in NCSP's Western Area, which will expand NCSP container throughput capacity from 170,000 TEU to 700,000 TEU. Upon completion of this project, the Group's container handling capacity in Novorossiysk will reach 1.2 million TEU per year. The anticipated timeframe for this project is 2015-2018.

Grain

Back to top

Expansion of NGT terminal facilities

Grain remains a staple cargo for NCSP Group, and as part of its new concept the Company plans to build up a reserve of grain handling capacity to secure its share of this market. With this goal in mind, the Group plans to expand the terminal facilities of NGT in 2012-2014. There are plans to increase grain storage capacity to 188,000 tonnes from 120,000 tonnes with the construction of new silos; install a third ship loading machine, overhaul berths, and build a fourth receiving line for grain trucks. These measures will help to expand grain throughput capacity at NGT by 2 million tonnes to approximately 7-8 million tonnes. The future of this project will be confirmed following the technical audit.

Iron ore

Back to top

NCSP Group plans to create a unique service for producers of iron ore by building a universal terminal for transshipment of iron ore, coal and mineral fertilizers, with projected capacity of up to 12 million tonnes per year, in NCSP's Central Area. This project is scheduled for 2015-2016.

A prerequisite for its implementation is increasing the loading rate to 50,000 tonnes per day, with the capability of loading ships with DWT of up to 120,000 tonnes. With this goal in mind, the company carried out dredging works last year that made it possible to load a bulk carrier with DWT of 114,000 tonnes at NCSP's Eastern Pier in November 2011.

Other cargo

Back to top

In order to more efficiently utilize existing facilities, the Company plans to redirect transshipments of metals, timber products (possibly), perishables, outsized cargo and other types of cargo to NCSP's Eastern Area and NSRZ in 2013-2016, which will require updating their equipment.

Primorsk

Back to top

One of the projects that NCSP Group is considering is a long-term program for the construction of terminals in Primorsk to handle oil products, containers, general and bulk cargo, the potential handling capacity for which is tentatively estimated at respectively 22 million tonnes, 1 million-2 million TEU, and 11 million tonnes.

The main goals of these projects would be to build a universal deepwater port in Russia's Northwest, set the stage for increasing, the country's export potential, and diversify the Company's business.