HomeFeedbackSite mapRussian version

 

JSC NLE completed the reconstruction of its timber and container terminals in 2008 in line with its Strategic Development Plan.

 

The company implemented the $86.4 million project to Increase Container Terminal Capacity over a period of two years, during which the terminal continued to operate normally. The container terminal’s throughput capacity increased to 350,000 TEU per year as a result of the reconstruction.

 

The $14.8 million project to increase Timber Cargo Transshipment was completed in 12 months, increasing capacity from 2.2 million cubic meters to 3 million cubic meters per year.